Implementation Plan

Use this before writing or editing any implementation plan declaration block.
This skill owns plan authoring vocabulary and declaration acceptance. Use
process-gates for execution-time preflight, step closeout, commit, push, and
completion gates.

Vocabulary

  • Task — the unit that owns a worktree, branch, and push policy. One task
    produces one PR unless the user or plan explicitly declares otherwise.
  • Phase — an ordered sub-unit inside a task. Phases share the task's
    worktree, branch, and PR. A phase never declares its own worktree, branch, or
    push policy.
  • Step — the smallest commit-sized unit, inside a phase or directly inside
    a task.

If a supposed phase needs its own branch, worktree, or PR, it is a task. Rename
or restructure it before execution.

Required Declaration Block

Every implementation plan must declare these seven fields before Step 1. They
split into two groups by who owns them and when they are set.

Planning intent — author-set at authoring time:

  • Execution mode: auto-continue or human-review-gated
  • Human review between tasks: yes or no
  • Push policy: no push, push after task, or push at closeout

Execution lock — executor-set at execution start:

  • Worktree mode: create new, reuse existing, or none
  • Expected worktree: a concrete path, a single resolvable pattern, or
    set at execution
  • Expected branch: a concrete branch name, a single resolvable pattern, or
    set at execution
  • Preflight check: unchecked while authoring; checked only after verified
    execution preflight evidence exists

The author sets the planning-intent fields. The executor sets the execution-lock
fields against the real session at execution start. An author may pre-fill the
execution lock only when authoring and execution are the same session and
worktree.

This does not relax the rule that every field is declared before Step 1: the
executor populates the lock at execution start, which precedes Step 1. The
split assigns ownership and timing; it does not move any field past Step 1.

A concrete live branch (or worktree path) is required for Expected branch and
Expected worktree only when authoring and execution are the same session. A
plan authored for separate or later execution MUST use the pattern form (e.g.
claude/<feature>-impl-*) or the literal set at execution, never a pinned
authoring branch — that branch goes dead once the plan is committed or merged,
and a later executor that honors it stalls against a guard meant to protect
execution.

Do not invent declaration values. Values like standard, normal, phase branch, or push at the end of each phase as one PR fail the declaration
check. The literal set at execution is the one allowed deferral marker for
Expected worktree and Expected branch; it is not an invented value and does
not fail the check.

Plan Lifecycle

A plan runs in one of two lifecycle modes. They differ only in whether the
execution lock can be concrete at authoring time.

  • Same-session — authored and executed together. Authoring and execution
    share one session, worktree, and branch. The execution lock may be concrete:
    the author records the real worktree and branch, and Preflight check is
    satisfied once execution preflight evidence exists.
  • Deferred — authored, committed/merged, executed later. The plan is
    authored in one session and executed later in a different session and branch.
    At authoring the execution lock is intent only: express Expected worktree/Expected branch as a pattern or set at execution, never a pinned
    authoring branch (which goes dead once the plan is committed or merged). The
    executor re-establishes the lock against the real session at execution start —
    see process-gates for the execution-start re-validation gate.

Deferred-lock declaration example

A plan authored now for execution in a later session declares the execution lock
as intent only. The author sets the planning-intent fields; the execution-lock
fields use the pattern or set at execution form, and Preflight check is left
for the executor:

Execution mode: auto-continue
Human review between tasks: no
Push policy: push at closeout
Worktree mode: create new
Expected worktree: set at execution
Expected branch: claude/<feature>-impl-*
Preflight check: [ ] (executor establishes the lock at execution start)

Because Expected branch is a pattern (or set at execution), merging this plan
before execution leaves no concrete branch to go stale. The executor resolves
both lock fields against the real session per the process-gates Implementation
Preflight Gate. Do not pin the authoring branch here — that is the same-session
form, and it goes dead once the plan is merged.

Acceptance Checklist

Run this checklist before Step 1 of any implementation plan. Halt on any
failure and fix the plan first.

  • All required declaration fields are present and non-empty.
  • The declaration block respects the planning-intent vs execution-lock split:
    planning-intent fields are author-set; execution-lock fields are executor-set at
    execution start, and are pre-filled at authoring only when authoring and
    execution are the same session and worktree.
  • Worktree mode is exactly one of create new, reuse existing, none.
  • Push policy is exactly one of no push, push after task,
    push at closeout.
  • Execution mode is exactly one of auto-continue,
    human-review-gated.
  • If the plan has phases, no phase declares its own worktree, branch, or
    push policy.
  • Expected worktree and Expected branch resolve to one task-level target,
    not a different target per phase.
  • If Expected branch names a concrete branch, this plan is executed and
    pushed from that branch in this session; otherwise it is a pattern or
    set at execution.
  • A plan intended to be committed/merged before execution MUST NOT pin a
    concrete authoring branch as Expected branch.
  • Push cadence aligns with task boundaries, not phase boundaries.

Existing Plan Migration

When interacting with an existing plan, reconcile its declaration block against
the checklist before continuing. Do not sweep every old plan preemptively; fix
plans at the moment they are edited or executed.

If a legacy plan describes per-phase worktrees, branches, or PRs, either:

  • rename those units to tasks, or
  • merge them into one task whose phases share one worktree, branch, and PR.

When executing a previously-committed or merged plan, treat its execution lock as
intent, not as a live target: re-establish Expected worktree/Expected branch
against the current session per the Plan Lifecycle deferred mode and the
process-gates execution-lock realignment step. A pinned authoring branch that no
longer exists is replaced, not honored as a blocker.